SMED: how to cut changeover time step by step
SMED is a method for cutting changeover time by separating what can only be done with the machine stopped (internal setup) from what can be done while it is still running (external setup). The stages are observe, separate, convert internal to external, and streamline what's left. Reductions of 40% to 70% in the first round are common when changeovers have never been studied.
This guide teaches the full method. If you'd rather start from a ready-made tool, we show the OEE spreadsheet with Pareto at the end. See the ready-made tool
Guilherme Rodrigues ItinoseUpdated 7 min read
Key takeaways
- Film and time the changeover before changing anything.
- Anything that can be done while the machine runs should leave the downtime.
- Offline tool presetting and standard fixturing usually bring the biggest gains.
- A slow first good part is part of the changeover and belongs in the study.
- Shorter changeovers only become money if freed capacity is used or batches shrink.
In many plants, machines spend more time being set up than producing. A CNC lathe with two 90-minute changeovers per shift loses about three hours a day without cutting a chip. Worse, that time is usually treated as unavoidable.
SMED (Single-Minute Exchange of Die) is the best-known method for attacking the problem. This article presents it as a technical study: the problem, the background, the stages, a worked example with fictitious numbers, the economic impact and what to do so the gain doesn’t vanish within three months.
Introduction: the hidden cost of changeovers
Changeovers hurt in three ways at once:
- They cut capacity: an hour in setup is an hour not producing
- They push large batches: if changing over is slow, the reflex is to run bigger batches to “make up for it”, raising inventory and lead time
- They make small batches expensive: in a quote, setup is divided by quantity, so low-volume parts cost more
Shorter changeovers attack all three. That’s why SMED appears in almost every lean implementation, not only in high-volume industries.
Background: internal and external setup
The method grew out of Shigeo Shingo’s work on press die changes and rests on a simple distinction:
- Internal setup: tasks that can only happen with the machine stopped. Example: removing the chuck jaws, mounting new ones, touching off tools on the machine.
- External setup: tasks that can happen while the machine is still running the previous job. Example: staging tools, fetching the program, gathering gauges.
In most plants that have never studied their changeovers, nearly everything is done as internal. The operator stops the machine and only then goes looking for tools, wrenches and the drawing. SMED’s first gain comes from fixing that, and it costs almost nothing.
The four stages of SMED
Stage 0: observe and measure
Film a complete changeover, from the last good part of the previous job to the first good part of the next. That’s the definition that matters: the changeover ends when the first approved part comes off, not when the spindle starts.
Then watch the video with the operator and log every task with its duration. The operator must be involved: they know the problems and will run the new standard.
Stage 1: separate internal from external
For each task, ask: can this be done while the machine runs? If so, move it before or after the stop. Correct tools on the cart, program checked, gauges ready, material for the next order beside the machine.
Stage 2: convert internal to external
Some tasks look internal but can change nature with some preparation. Classic examples:
- Offline tool presetting with a presetter or simple fixture, instead of touching off each tool on the machine
- Pre-prepared jaws or fixtures, stored ready for the next part
- Programs proven in simulation before the changeover, instead of “trying” on the machine
Stage 3: streamline what’s left
Whatever remains internal should get faster:
- Quick-release or quarter-turn clamps instead of long bolts
- Stops and locating pins that remove adjustments
- Standard wrenches: one size for the whole changeover
- First-part checks with go/no-go gauges where it makes sense
- Two people on the longest changeovers
Worked example: CNC lathe changeover
Fictitious values, based on a typical lathe changeover with a jaw change.
| Task | Before (min) | Type after | After (min of downtime) |
|---|---|---|---|
| Fetch tools and jaws | 15 | external | 0 |
| Find and load program | 7 | external | 0 |
| Remove jaws and tools | 10 | internal, streamlined | 6 |
| Mount and bore soft jaws | 20 | converted (jaws ready) | 8 |
| Mount and touch off tools | 18 | converted (presetting) | 6 |
| First part, measurement and adjustment | 25 | internal, streamlined | 12 |
| Total machine downtime | 95 | 32 |
Downtime fell from 95 to 32 minutes, about 66%. Note that stage 1, which is pure organization, removed 22 minutes with no investment.
Effect on OEE and cost
Assume two changeovers per 8-hour shift (480 minutes) and no other stops, to isolate the effect:
- Before: 190 minutes of setup, availability of (480 − 190) ÷ 480 ≈ 60%
- After: 64 minutes of setup, availability of (480 − 64) ÷ 480 ≈ 87%
That’s 126 minutes a day, or about 44 hours a month over 21 working days. At a machine hour rate of $69, that’s roughly $3,000 a month in capacity.
Careful: that money only appears if the capacity is used. There are three ways to capture the gain:
- Produce more on the same machine, if demand exists.
- Cut batch sizes and inventory, changing over more often within the same total setup time.
- Postpone buying another machine or adding a shift.
To track the effect, setup needs to appear as a stop reason in your downtime Pareto, and availability in your OEE calculation.
How to sustain the gain
SMED fails less often during rollout than during the months after. Without a standard, changeovers drift back to the old time. To prevent that:
- Visual setup instructions, with photos and sequence, at the machine
- A setup cart with a marked place for every tool and wrench
- Changeover time measured every time, not only during the project
- A monthly review of the longest changeovers, with the operators
- Cross-training, so the standard doesn’t depend on one person
Common mistakes
Starting by buying equipment
Presetters and quick clamps help, but stage 1 is free and usually brings most of the early gain. Buying before organizing wastes money.
Timing only until the spindle starts
If the first part takes 25 minutes of adjustments, the changeover wasn’t over when the program ran. Measure until the first approved part.
Doing it without the operator
A standard designed in the office and handed over tends to be ignored. Operators must help create it.
Not deciding what to do with the freed time
Without a decision on capacity, batch size or investment, freed time becomes idle time, and the project appears to have achieved nothing.
Four-week rollout plan
- Week 1: pick the machine with the most setup hours in the Pareto. Film two changeovers.
- Week 2: analyze with the operator. Separate internal and external and apply the no-cost changes.
- Week 3: convert what you can (presetting, ready jaws, simulated programs).
- Week 4: standardize, create the visual instruction and start timing every changeover.
Then repeat on the next machine. If manual timing is a burden, changeover time can be read straight from the CNC control. That’s what CNC Pulse does: monitoring that shows each machine’s stops and OEE with no manual logging.
Conclusion
SMED turns changeovers from an unavoidable cost into a controllable variable. The internal/external distinction, applied with the operator and the video in hand, typically cuts 40% to 70% of changeover time in the first round, with little investment.
The example showed a drop from 95 to 32 minutes and availability rising from 60% to 87%. The final step is the one most often forgotten: decide how to use the freed time, and keep measuring so the result doesn’t disappear.
When to outsource this
- You want changeover time measured automatically from the machine, without manual logging
- You need standardized visual setup instructions for several operators
When not to
- The machine runs one part all year and almost never changes over
FAQ
What does SMED stand for?
Single-Minute Exchange of Die: changing over in a single-digit number of minutes. The target is under 10 minutes, but the method pays off even when that number isn't reached.
What's the difference between internal and external setup?
Internal setup requires the machine to be stopped, such as changing chuck jaws. External setup can be done while it runs, such as staging tools and checking the program.
Is SMED only for presses?
No. It started with presses but applies to lathes, machining centers, injection molding, press brakes, filling lines and any product change.
How long does an SMED project take?
A first round on one machine usually takes two to six weeks, covering filming, analysis, simple changes and standardization.
Sources
- Single-minute exchange of die (Wikipedia) (accessed November 16, 2026)
- Overall equipment effectiveness (Wikipedia) (accessed November 16, 2026)
- Lean manufacturing (Wikipedia) (accessed November 16, 2026)
Send us one drawing
We return a review with issues found, suggested fixes and a fixed-price scope.