New product development process: stages, gates and schedule

Developing an industrial product with less risk means splitting the project into stages (requirements, concept, detailed design, prototype and validation, industrialization and launch) separated by gates: decision meetings with defined criteria to go, adjust, hold or stop. Each stage delivers verifiable documents, and the schedule is built from those deliverables.

This guide teaches the full method. If you'd rather start from a ready-made tool, we show the Engineering project schedule with Gantt at the end. See the ready-made tool

Guilherme Rodrigues ItinoseUpdated 6 min read

Key takeaways

  • Changing a design gets more expensive the further the project goes.
  • Every gate needs criteria written before the meeting, not during it.
  • Measurable requirements prevent subjective arguments at validation.
  • A prototype validates function; a pilot run validates the manufacturing process.
  • The schedule comes from each stage's deliverables, not from an imposed date.

Many industrial products are born like this: the owner has an idea, a designer draws it, the shop builds a prototype, and the product keeps being fixed while it is already being sold. That works for simple things. For products with more parts, suppliers and requirements, the usual result is delay, higher cost than planned and a product that is never quite “finished”.

This article presents a stage-and-gate development process adapted to small and mid-sized manufacturers. It’s organized like a technical study: the problem, the background, the stages and their deliverables, gate criteria, an example schedule and common mistakes. The example is hypothetical.

Introduction: why developing without a method costs more

The cost of changing a product grows as the project advances. Changing a dimension at concept stage costs a conversation. Changing the same dimension after the stamping die is made costs the die. Changing it after the product has shipped costs recalls, warranty and reputation.

So the purpose of a development process is to bring decisions forward: find problems while they’re still cheap to fix.

Background: stages and gates

The stage-gate (or phase-gate) model splits a project into two kinds of element:

  • Stages: periods of work with defined deliverables
  • Gates: decision meetings where management checks deliverables against written criteria and decides

There are four possible gate decisions:

  1. Go: deliverables approved, next stage released
  2. Adjust: proceed with open items logged, with a deadline and owner
  3. Hold: wait for information or resources
  4. Kill: the project no longer makes technical or commercial sense

Killing a project at gate 2 isn’t failure; it’s savings. Failure is discovering at pilot run that the product has no market or costs twice the target.

In automotive, the same logic appears in APQP (Advanced Product Quality Planning), which organizes development in phases and requires part approval before production. A small manufacturer can use a simplified version.

The six stages and their deliverables

Stage 0: opportunity

Why develop this product? For whom? How many can you sell, at what price? Deliverables: customer problem statement, volume and target price estimate, target manufacturing cost.

Stage 1: requirements

What the product must do, in numbers. “Robust” isn’t a requirement; “carries 200 kg with no more than 2 mm deflection” is. Deliverables: measurable requirements list, applicable standards, constraints (size, weight, power), acceptance criteria.

Stage 2: concept

Two or three solutions compared against requirements. Deliverables: sketches or simplified models, decision matrix, cost estimate for each concept, main technical risks. A clear brief for your engineering partner at this stage saves months of back-and-forth.

Stage 3: detailed design

The chosen concept becomes a complete 3D model and manufacturing drawings. Deliverables: reviewed models and drawings, bill of materials, design failure mode analysis (DFMEA), manufacturability review with suppliers, calculation or simulation of critical parts.

Stage 4: prototype and validation

Build and test against stage 1 requirements. Deliverables: prototype, test plan and report, approved design change list, updated drawings.

Stage 5: industrialization

Prepare series production: tooling, fixtures, suppliers, instructions and controls. Deliverables: defined process, process FMEA, control plan, pilot run made with the final process, actual cost compared with target cost. The drawings released here should form a complete manufacturing documentation package.

Stage 6: launch and follow-up

Release for sale and monitor the first months: complaints, warranty, cost, lead time. Deliverables: post-launch report and lessons learned.

Gate criteria

Gate Core question Typical criteria
G1 (after opportunity) Is it worth studying? Market identified, target price and cost plausible
G2 (after requirements) Do we know what to build? Measurable requirements, standards mapped
G3 (after concept) Which solution do we pursue? Concept meets requirements, acceptable technical risk, estimated cost within target
G4 (after design) Can we prototype? Drawings reviewed, DFMEA done, suppliers consulted
G5 (after validation) Does it work? Tests passed, changes incorporated
G6 (after pilot run) Can we sell it? Capable process, acceptable actual cost, documentation released

Criteria must be written before the meeting. If they’re defined during it, the decision becomes a negotiation.

Example schedule

Hypothetical project: a conveyor module for a packaging line, developed by a machine builder with three engineers.

Stage Duration (weeks) Estimated engineering hours
0. Opportunity 2 30
1. Requirements 3 60
2. Concept 4 120
3. Detailed design 6 320
4. Prototype and validation 6 160
5. Industrialization 4 140
Total to launch 25 830

Three notes on the schedule:

  1. Detailed design holds almost 40% of the hours. That’s where outsourcing part of the work pays off most.
  2. Prototype lead time depends on outside suppliers (machining, sheet metal). Add buffer there.
  3. Holidays and vacations must be counted in working days, or the deadline is wrong from day one.

Common mistakes

Skipping requirements

Starting to draw without measurable requirements leads to subjective validation: “does it look good?” becomes an endless debate.

Gates without criteria

A gate meeting that only “presents progress” decides nothing. Without criteria, every project goes ahead, including those that should stop.

Mistaking a prototype for a product

A hand-built prototype adjusted on the bench doesn’t prove the product can be made in series. That’s what the pilot run is for.

Ignoring cost until the end

Finding out the real cost at industrialization is too late. Estimate cost at every stage and compare it with the target at each gate.

Leaving documentation for later

Outdated drawings at pilot run are a guaranteed source of wrong parts. Documentation moves with each stage.

How to apply it in a small company

  1. Use the six stages, with lean deliverables: a one-page requirements list is already a big step.
  2. Run gates with no more than four people: owner or director, engineering, production and sales.
  3. Keep a visual schedule with planned and actual hours per stage.
  4. Record lessons learned and review them at the start of the next project.

When engineering hours run short in stages 3 to 5, Downway provides CAD engineering and detailing and manufacturing documentation, integrated with your team’s schedule.

Conclusion

Stage-and-gate development isn’t bureaucracy; it’s how you make expensive decisions while they’re still cheap. Measurable requirements, gate criteria written in advance and a clear line between prototype and pilot run solve most delays and cost overruns.

The example showed a 25-week project of about 830 hours, with detailed design taking the largest share. With the schedule tied to each stage’s deliverables, management sees the project as it is, not as it would like it to be.

When to outsource this

  • Your team lacks engineering hours for detailed design and documentation
  • You need to turn a concept or hand-built prototype into manufacturing drawings

When not to

  • The product is a small variation of something existing, with low technical risk

FAQ

What is stage-gate?

A management model in which a project moves through stages separated by decision points called gates. At each gate, management decides to go, adjust, hold or kill the project based on defined criteria.

How long does industrial product development take?

It depends on complexity. Simple mechanical products can take three to six months; equipment with electronics, certification or many suppliers can take more than a year.

Does a small company need a formal process?

It needs a simple one. Even with three or four people, defined stages, deliverables and gates prevent rework and decisions made too late.

What's the difference between a prototype and a pilot run?

A prototype proves the product works. A pilot run proves it can be made with the final process, tooling and suppliers, at the expected quality and cost.

Sources

  1. Phase-gate process (Wikipedia) (accessed November 16, 2026)
  2. New product development (Wikipedia) (accessed November 16, 2026)
  3. Advanced product quality planning (Wikipedia) (accessed November 16, 2026)
  4. Design for manufacturability (Wikipedia) (accessed November 16, 2026)

Send us one drawing

We return a review with issues found, suggested fixes and a fixed-price scope.

Real project experience

Websites we have launched

A few businesses that trusted Downway to build their digital presence.